How long does a kitchen renovation take?

A stage-by-stage guide to how long a kitchen renovation takes, what causes delays and how to manage without a kitchen.

How long does a kitchen renovation take?

A straightforward kitchen refit, where the layout stays much the same, usually means one to three weeks of work in your home. A bigger renovation, with a wall coming down, the sink moving or a stone worktop being made to measure, takes longer. And the design and ordering before anyone starts work often takes longer than the fitting itself.

This post walks through each stage of a kitchen renovation, roughly how long each one takes, what tends to slow things down, and how to cope without a kitchen while the work goes on.

Before work starts: design and ordering

Every kitchen starts with measuring, design and a quote. Then you choose the units, worktops, tiles and appliances, and they need to be ordered. Kitchens bought ready-made from a showroom or trade counter can arrive quickly, but made-to-order units often take several weeks, so ask your supplier for a delivery date before you set a start date.

It is best to have everything delivered and checked before the old kitchen comes out. That way you aren't left without a kitchen while you wait for a missing cabinet or a damaged door to be replaced.

If you'd like a new kitchen in the spring, the winter months are a good time to do the design and ordering. Riverside Construction Group isn't tied to one supplier, so we can fit a kitchen you've chosen yourself, including from suppliers such as IKEA, Howdens or Wren.

What happens on site, stage by stage

Strip-out

Taking out the old units, worktops and tiles usually takes a day or two. The water, electrics and any gas supply to the old kitchen are made safe first. In older homes this is often when hidden problems come to light, such as old wiring or rotten floor timbers. Our post on problems to expect when renovating a Victorian house explains the common ones.

Structural work, if there is any

Knocking through to a dining room means taking out a wall, and if that wall is load-bearing (holding up part of the house above it), a steel beam has to go in to carry the load. This is a structural change, so it needs Building Regulations approval and a structural engineer's calculations, and building control inspects the work. Allow extra days on site, and extra weeks beforehand for the approval.

First fix

"First fix" means the pipes and cables that go inside the walls and floor before they are finished: water and waste pipes, new sockets and lighting circuits, the cooker supply and any gas pipe to the hob. In England, adding a new electrical circuit in a kitchen has to be notified to building control, which a registered electrician does as part of the job. Any gas work must be done by a Gas Safe registered engineer.

Plastering

Once the pipes and cables are in, the walls and ceiling are made good or skimmed with fresh plaster. New plaster needs to dry before it can be painted or tiled. A thin skim dries in a few days, but thicker repairs take longer, and rushing this stage causes cracked paint and tiles that don't stick properly.

Fitting the units and worktops

The base and wall units go in next, usually over a few days. Laminate and wooden worktops are cut and fitted on site at the same time. Stone and quartz worktops are different: they can only be measured once the base units are in, and are then made to size, which often leaves a gap of a week or two before they are fitted. Until the worktop is in, the sink and hob can't be fully connected.

Second fix and finishing

Finally, the splashback or tiles go up, the sink, taps and hob are connected, the appliances are fitted and tested, and the sockets and lights are fitted to the cables put in at first fix. A careful final check for leaks, loose doors and gaps in the sealant should come before you sign the job off.

What makes a kitchen renovation take longer

Most delays come from a few familiar causes:

  • Moving the sink or changing the layout, especially if it means a new connection to the main waste pipe, which also needs Building Regulations approval
  • Removing a load-bearing wall, which needs approval first, and if the beam sits in a wall you share with a neighbour, a party wall notice at least two months before work starts
  • Stone or quartz worktops, because of the wait while they are made
  • Late, wrong or damaged deliveries
  • Hidden problems found once the old kitchen is out
  • Changes of mind once work has started, such as moving sockets after the walls are plastered

Living without a kitchen

For most people this is the hardest part, so it is worth planning for:

  • set up a temporary kitchen in another room with the kettle, microwave, toaster and, if you can move it, the fridge
  • plan simple meals for the weeks of the work, and stock up before the strip-out
  • do the washing up in a utility room or a bathroom basin, with a washing-up bowl
  • ask which days the water, power or gas will be off, as there are usually a few short periods during first fix and second fix
  • keep doors to the rest of the house closed, as cutting and sanding create dust

How to keep your kitchen on schedule

The single biggest help is making every decision before work starts: units, worktops, tiles, appliances, and exactly where you want sockets and lights. The other is having one team handle every trade, so no one is waiting for the electrician or plasterer to turn up. At Riverside Construction Group, every trade on a kitchen job, from structural work to plumbing, electrics and tiling, is done by our own team, with one point of contact throughout. If your new kitchen is part of a bigger project, our home renovation service brings the whole job under one programme.