A straightforward kitchen refit, where the layout stays much the same, usually means one to three weeks of work in your home. A bigger renovation, with a wall coming down, the sink moving or a stone worktop being made to measure, takes longer. And the design and ordering before anyone starts work often takes longer than the fitting itself.
This post walks through each stage of a kitchen renovation, roughly how long each one takes, what tends to slow things down, and how to cope without a kitchen while the work goes on.
Every kitchen starts with measuring, design and a quote. Then you choose the units, worktops, tiles and appliances, and they need to be ordered. Kitchens bought ready-made from a showroom or trade counter can arrive quickly, but made-to-order units often take several weeks, so ask your supplier for a delivery date before you set a start date.
It is best to have everything delivered and checked before the old kitchen comes out. That way you aren't left without a kitchen while you wait for a missing cabinet or a damaged door to be replaced.
If you'd like a new kitchen in the spring, the winter months are a good time to do the design and ordering. Riverside Construction Group isn't tied to one supplier, so we can fit a kitchen you've chosen yourself, including from suppliers such as IKEA, Howdens or Wren.
Taking out the old units, worktops and tiles usually takes a day or two. The water, electrics and any gas supply to the old kitchen are made safe first. In older homes this is often when hidden problems come to light, such as old wiring or rotten floor timbers. Our post on problems to expect when renovating a Victorian house explains the common ones.
Knocking through to a dining room means taking out a wall, and if that wall is load-bearing (holding up part of the house above it), a steel beam has to go in to carry the load. This is a structural change, so it needs Building Regulations approval and a structural engineer's calculations, and building control inspects the work. Allow extra days on site, and extra weeks beforehand for the approval.
"First fix" means the pipes and cables that go inside the walls and floor before they are finished: water and waste pipes, new sockets and lighting circuits, the cooker supply and any gas pipe to the hob. In England, adding a new electrical circuit in a kitchen has to be notified to building control, which a registered electrician does as part of the job. Any gas work must be done by a Gas Safe registered engineer.
Once the pipes and cables are in, the walls and ceiling are made good or skimmed with fresh plaster. New plaster needs to dry before it can be painted or tiled. A thin skim dries in a few days, but thicker repairs take longer, and rushing this stage causes cracked paint and tiles that don't stick properly.
The base and wall units go in next, usually over a few days. Laminate and wooden worktops are cut and fitted on site at the same time. Stone and quartz worktops are different: they can only be measured once the base units are in, and are then made to size, which often leaves a gap of a week or two before they are fitted. Until the worktop is in, the sink and hob can't be fully connected.
Finally, the splashback or tiles go up, the sink, taps and hob are connected, the appliances are fitted and tested, and the sockets and lights are fitted to the cables put in at first fix. A careful final check for leaks, loose doors and gaps in the sealant should come before you sign the job off.
Most delays come from a few familiar causes:
For most people this is the hardest part, so it is worth planning for:
The single biggest help is making every decision before work starts: units, worktops, tiles, appliances, and exactly where you want sockets and lights. The other is having one team handle every trade, so no one is waiting for the electrician or plasterer to turn up. At Riverside Construction Group, every trade on a kitchen job, from structural work to plumbing, electrics and tiling, is done by our own team, with one point of contact throughout. If your new kitchen is part of a bigger project, our home renovation service brings the whole job under one programme.